Objectives: Construction and installation of the steel structures, equipment, and related components for three reheating furnaces with a capacity of 340 tons per hour.
Project Name: Construction, Transportation, and Installation of the Steel Structures for Three Reheating Furnaces with a Capacity of 340 Tons per Hour
Client: Kayson
Contract Type: PC
Commissioning Year: 2023
Location: Mobarakeh Steel Complex





Preparation of the 3D model, drawings, and documentation for the steel structures; fabrication of the steel structures for the furnaces with a total weight of 1,914,000 kg; installation of the steel structures, equipment, and related components for three reheating furnaces with a total installation weight of 4,077,000 kg and a capacity of 340 tons per hour; delivery of the project and guarantee of its performance at the Hot Rolling Mill No. 2 of Mobarakeh Steel Company.