Manufacturing, Transportation, and Installation of Steel Structures for Three Preheating Furnaces with a Capacity of 240 Tons per Hour

About the Project

Objectives: Replacement of the movable frame based on the foreign technology design, as well as replacement and refurbishment of the fixed frame of Reheating Furnaces No. 3 and No. 4 at the Hot Rolling Mill.

Project Information

Client: Mobarakeh Steel Company

Contract Type: EPC

Commissioning Year: 2023

Location: Mobarakeh Steel Complex

Project Details

Design and engineering for the reconstruction of Reheating Furnaces No. 3 and No. 4 of the Hot Rolling Mill, including the procurement and fabrication of equipment; as well as the replacement of the movable frame, replacement and refurbishment of the fixed frame of the aforementioned furnaces, installation of equipment, testing, commissioning, and execution of all activities related to the reconstruction project of Walking Beam Furnaces No. 3 and No. 4 of the Hot Rolling Mill.